Lea Bridge Gasworks development stalls due to ‘construction industry issues’

Residents fear developer Berkeley is hoping to submit a new planning application for even taller towers
By Local Democracy Reporter Josh Mellor

A CGI image of the currently planned scheme (credit: Berkeley)
A CGI image of the currently planned scheme (credit: Berkeley)

Construction has halted on hundreds of homes at Lea Bridge Gasworks “for the foreseeable future”, with neighbours fearing the developer wants to add more flats.

Developer Berkeley’s plans for 573 homes in blocks of up to 18 storeys tall on the former gasworks site were approved in 2020, with construction due to begin this year.

But in May, Berkeley told residents it had pulled out all of its machinery and stood down its team due to “multiple global and national issues” affecting the construction industry.

An email from the developer’s technical manager, seen by the Local Democracy Reporting Service (LDRS), said ongoing issues around “supply chains, labour availability and material prices” have worsened due to the war in Ukraine.

They added: “At present both our internal team and external team of consultants have been stood down and reallocated to other projects.”


This story is published by Waltham Forest Echo, Waltham Forest's free monthly newspaper and free news website. We are a not-for-profit publication, published by a small social enterprise. We have no rich backers and rely on the support of our readers. Donate or become a supporter.


Trees have already been cleared from the site (credit: Ranjan Sen)

However, resident Simon Rix, 57, said those living near the site are worried the real reason is that the two 26-storey towers being built at nearby Lea Bridge Station have set a new precedent for taller buildings.

He added: “We’re relieved that they’re not doing it at the moment but we’re also worried they may have plans for the future for taller buildings and cheaper materials.”

A spokesperson for Berkeley told the LDRS the company never makes public comments about the timetable of developments.

They said the project is still going ahead as planned and dismissed any speculation as mistaken.

Community before Construction member Ben Copsey, who lives nearby and campaigned for better management of the contaminated soil, said: “My understanding of it after reading about remediation they’re proposing… is it’s too expensive for them.

“So in my view what they are doing is taking a step back from that to say to the council ‘if you want this application to be built, you need to lower the offer of social housing or green space’.”


No news is bad news 

Independent news outlets like ours – reporting for the community without rich backers – are under threat of closure, turning British towns into news deserts. 

The audiences they serve know less, understand less, and can do less. 

If our coverage has helped you understand our community a little bit better, please consider supporting us with a monthly, yearly or one-off donation. 

Choose the news. Don’t lose the news.

Monthly direct debit 

Annual direct debit

£5 per month supporters get a digital copy of each month’s paper before anyone else, £10 per month supporters get a digital copy of each month’s paper before anyone else and a print copy posted to them each month.  £50 annual supporters get a digital copy of each month's paper before anyone else.

Donate now with Pay Pal

More information on supporting us monthly or annually 

More Information about donations

Tags